On many modern browsers holding down the CTRL key and using
the mouse wheel allows sizing these pages to suit
|
Structures in orders, words and
standards This page was originally triggered off by an enquiry made to me about the effect of specifying BS5709 in path orders. There are two key questions: And there is an auxiliary question: If making use of BS5709 (the British Standard [BS] for Gaps Gates and Stiles) should the form '...to BS5709.' or the form '...to BS5709:2006.' be used? This issue is largely independent of 1 and 2 above and is dealt with at the end of this paper. Some of what follows may seem like complicated answers to
simple questions. But the nature of BS5709, which since 2001 has required the
‘least restrictive option’ for compliant structures, does need to be understood
in order for the benefits of specifying it to be realised.
General. I do not intend to go deeply into the oughts or ought nots behind putting structures into orders, questions like the public's ability to object to orders but not to S147 permissions. Decisions on structures in orders may ultimately depend on what flexibility can be put lawfully into orders, that is whether a convergence of the currently rather differently constrained processes, orders and permissions, can be made. This may require statutory guidance or legislation or both. For example a new statute could require the least restrictive option to be achieved by making limitations in orders variable, or if variability was believed to be lawful under present law, then new regulations could suggest appropriate words. And S147 permissions might have a limited public consultation stage. It may be that in future structures in orders should be confined to things like wears, essential steps and railings (and of course variable limitations like the right to pile wood on some part of the path). S147 could then be extended as a single regime with the public in the loop to deal with all the other structural limitations. But that would be for the future. Authorisation within an order.
There are certain authorisations which cannot lawfully be made except within an order, for example where a diversion or creation is desired by all parties and the landholder will only agree if a structure is allowed at a particular place, say at a private garden where neither side of the structure is agricultural but a dog proof gate cannot readily be avoided. Here the option of saying 'do them all by regulatory permission' is not at present available and the order mechanism just has to be used.
Authorisation
outside of an order. In these outside-of-order authorisations BS5709 does not have to be made a
requirement but it offers a very neat short cut with its inbuilt least
restrictive option requirement and simple field measurable compliance tests,
plus of course its allowing of a wide diversity of actual structural
designs, materials and methods. Past experience has shown that it is
necessary to say here that the illustrations in the BS are not designs to be
slavishly followed in shape, size, material or anything; they are simply
examples from a range of possible structures. So long as any structures are
least restrictive, kept free of barbed wire and meet the other BS functional
and field measurable requirements then any such design will comply. By
specifying BS5709, authorities are very rarely preventing local-character
structures. And they are making things easier for many of their staff
compared with the difficulties of specifying reviewing and policing
their home-grown and often set-in-time design specifications. In summary and in line with the above and current situation a
highway authority might reasonably be expected, also in line with HA80 S130
duties and so on, to have a rule that structures will normally only be
included in path orders when such structures could not be authorised by
other means subsequent to the order being confirmed. Hertfordshire for
example has such a rule.
In view of all the above it is suggested that at the present time orders which include structures as limitations (whether citing BS5709 or not) should in fact be the exception rather than the norm unless somehow the desired level of flexibility can be unequivocally built in.
2. When structures are included in orders, how should they be specified? Conformity with BS5709 should be aimed for whenever relevant structures actually need to be incorporated in path orders, this can assist landholders by more certainty, path users by better access, and highway authorities by simpler (and less costly) specification and simpler (and also less costly) enforcement. But it is important that the nature of BS5709, which since 2001 has required the ‘least restrictive option’ to apply on an ongoing basis, is understood in order for the benefits of specifying it to be realised. There is an information sheet at www.pittecrofttrust.org.uk (also mentioned above) and this is commended to help that understanding. Let us now take the case where the limitation does indeed need to go into the order, and BS5709 is to be cited. The words suggested at 1.B above were "The right of the landholder to erect a structure at point X conforming with BS5709" The words “The right of the landholder to erect” although slightly pedantic is suggested as best following the nature of most limitations in orders, something that may limit path use, but does not have to. The words “conforming with BS5709” i.e. the latest version, are suggested rather than “conforming with BS5709:2006” i.e. the 2006 version. This distinction is discussed below, but either form could be used so long as the implications are understood and accepted. So we are left with two apparently simple words “a structure” which rather surprisingly require a paragraph or two to themselves. "a structure"
But there are two difficulties to that, one specific to stiles. The stile difficulty is that BS5709 in relation to stiles is directed to the improvement of existing lawful stiles and their use as new structures requires exceptional circumstances (BS5709 3.1.3. & 4.6.1). It may be that a landholder is willing, but only if a stile is allowed, to agree a diversion or creation agreement that is overall in the public interest despite that stile. That might be considered exceptional circumstances if S147 could not be lawfully used. It may be of interest that the then Countryside Commission representative argued, in the discussions leading to the 2001 BS5709 edition, for it not to include stiles at all. But setting aside stiles and focussing instead on ‘kissing gate’ what harm would ‘a kissing gate to BS5709’ do? Well inherent in BS5709 is the ongoing requirement of the least restrictive option in relation to the need. So defining the structure as a kissing gate prevents compliance with BS5709 when or if it ceases to be the least restrictive option. So what would the words "The right of the landholder to erect a kissing gate at point X conforming with BS5709" mean if they were actually to be used? Probably something like ‘A kissing gate at point X to BS5709 requirements but not subject to the least restrictive structure rule’. Though it is obviously undesirable, there is nothing wrong with excluding parts of the standard if that exclusion is made plain. So those amended words would do in those cases and only those cases where the type of structure requires to be, or may be, permanent as well as being unable to be authorised outside of the order. But the least restrictive option is an important consideration, that concept is deeply embedded in the BS (written with landholder groups' involvement) it reflects government policy, helps deliver the Highways Authorities’ duty under HA80 s130, may help avoid DDA difficulties and is supported by the main user groups. So the words "The right of the landholder to erect a structure at point X conforming with BS5709" would seem to be much closer to optimum for use in orders. There is just one half way house that might help smooth paths as it were, that is where there is no especial intention always to have a particular structure but the initial form of structure is known and is in line with the least restrictive rule. In that case the words ‘initially a kissing gate’ might be added, giving all concerned information on what to expect as well as notice that the structure might change. So then we would have "The right of the landholder to erect a structure at point X conforming with BS5709, initially a kissing gate”. This is at the time of writing my preferred form, it tells the public what to expect to find at point X if the order is confirmed. It clarifies to the landholders what is initially authorised, but puts them on notice that it is not necessarily for ever, though they may well believe that in practice they won't be asked to change it. It doesn't confuse the general public by leaving out any reference to the type of structure. It should be noted that these words go, or should go, automatically onto the definitive statement. A requirement to put S147 permissions onto the statement or as a second best onto the local authority's web site would fulfil much the same purpose for limitations authorised by that means and help harmonise the two processes.
If any reader of this paper feels anything needs clarification or
correction or addition the author would be pleased to hear about it, email
to: chris@badfa.org.uk |
||||
http://www.badfa.org.uk/gates&stiles/structuresinorders.htm |
||||
| Top of Page latest changes 08 November 2008 BADFA Home page |